EAST HADDAM, LYME, OLD LYME — The Connecticut Department of Transportation started a milling and paving project yesterday on Rte. 156. This project, which will mill and pave 8.44 miles of the road from East Haddam to Old Lyme, begins with the milling, which will continue through June 23. Roadway paving will then commence July 7 and continue through July 22.
Motorists can expect lane closures on Rte. 156 beginning at Rte. 82 in East Haddam through Lyme, ending on Rte. 1 in Old Lyme. The regular work schedule for this project will be 7 a.m. to 5 p.m., Monday through Friday.
Drivers should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions.
Motorists are also requested to maintain a safe speed while driving in the construction area or when approaching it.